7 turbines · under construction · Lanarkshire
| Status | Under Construction |
|---|---|
| County / region | Lanarkshire |
| Turbines | 7 |
| Installed capacity | 46.2 MW |
| Turbine capacity | not recorded |
| Tip height | 200 m |
| Operator (or applicant) | Muirhall Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6363.
The application was determined in about 60 months. The register records a refusal in August 2017 before the scheme progressed. Permission was ultimately granted on appeal in December 2018. A planning permission on this site expired in March 2024. That works out at 6.6 MW per turbine on average.
See all wind farms in Lanarkshire.