Princes Gate Spring Water

2 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines2
Installed capacity1.6 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Princes Gate Spring Water
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 Project timeline Application submitted November 2011 Permission granted July 2013 Operational September 2014

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3378.

What the register tells us

The application was determined in about 20 months. The scheme has been operating for about 12 years. That works out at 0.8 MW per turbine on average.

Nearby

See all wind farms in Dyfed.