Ramsey Wind Farm Extension

4 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines4
Installed capacity8 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted November 2011 Permission granted May 2013 Under construction November 2014 Operational April 2015 Permission expired May 2018

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4414.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 5 months. A planning permission on this site expired in May 2018. The scheme has been operating for about 11 years. That works out at 2 MW per turbine on average.