Ranson Moor (phase 1)

3 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Fenpower Limited
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted July 2003 Permission granted April 2005 Under construction September 2006 Operational May 2007 Permission expired April 2011

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2952.

What the register tells us

The application was determined in about 21 months. Construction to first power took about 8 months. A planning permission on this site expired in April 2011. The scheme has been operating for about 19 years. That works out at 2 MW per turbine on average.