Reaps Moss Wind Farm

9 turbines · revised · Lancashire

Wind farm facts

StatusRevised
County / regionLancashire
Turbines9
Installed capacity9 MW
Turbine capacity1 MW
Tip heightnot recorded
Operator (or applicant)S B ENERGY LTD
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 Original scheme Application submitted June 1999 Refused February 2000 Later scheme Application submitted February 2007 Permission granted October 2009 Under construction October 2014 Operational March 2015

The register links a second scheme on this site (REPD ref 4655, Operational): 3 turbines · 3.4 MW each · 125 m tip height · applicant Infrared Capital Partners. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2609.

What the register tells us

The register records a refusal in February 2000 before the scheme progressed. That works out at 1 MW per turbine on average.