Red Gap Moor Wind Farm

5 turbines · operational · Cleveland

Wind farm facts

StatusOperational
County / regionCleveland
Turbines5
Installed capacity12.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Capital Dynamics
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted May 2009 Permission expired March 2010 Permission granted March 2011 Under construction May 2016 Operational February 2017

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4415.

What the register tells us

The application was determined in about 22 months. Construction to first power took about 9 months. A planning permission on this site expired in March 2010. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.