Red Tile

12 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines12
Installed capacity24 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Wind Prospect Developments
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 Project timeline Application submitted October 2003 Permission granted February 2005 Under construction May 2006 Operational December 2006

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3608.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 7 months. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.