Rhodders Wind Farm

6 turbines · operational · Clackmannanshire

Wind farm facts

StatusOperational
County / regionClackmannanshire
Turbines6
Installed capacity12 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)EDF/Wind Prospect
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted November 2011 Refused July 2013 Permission granted January 2014 Granted on appeal January 2014 Under construction August 2015 Operational February 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4223.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 6 months. The register records a refusal in July 2013 before the scheme progressed. Permission was ultimately granted on appeal in January 2014. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.