Rodbaston

2 turbines · operational · Staffordshire

Wind farm facts

StatusOperational
County / regionStaffordshire
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower
Turbine manufacturerSiemens Gamesa
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted July 2009 Permission granted December 2010 Under construction February 2016 Permission expired December 2016 Operational January 2017

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3673.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 11 months. A planning permission on this site expired in December 2016. The scheme has been operating for about 9 years. That works out at 2 MW per turbine on average.