Roos Wind Farm (Resubmission)

9 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines9
Installed capacity17.1 MW
Turbine capacity1.9 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted January 2009 Refused August 2009 Permission granted May 2010 Granted on appeal May 2010 Permission expired May 2011 Under construction March 2012 Operational April 2013

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3835.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 13 months. The register records a refusal in August 2009 before the scheme progressed. Permission was ultimately granted on appeal in May 2010. A planning permission on this site expired in May 2011. The scheme has been operating for about 13 years. That works out at 1.9 MW per turbine on average.