🌬️ Onshore wind farm

Roos Wind Farm (Resubmission)
Humberside

Recorded in WhichWindTurbine: 9 wind turbines in operation. Point the app at one of them to see its profile in real time.

9
turbines
17.1 MW
MW total
1.9 MW
per turbine

📍 9 turbines mapped — each dot is a turbine recorded in the database. Average position: 53.74565 N · 0.06784 W.

Roos Wind Farm (Resubmission)

9 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines9
Installed capacity17.1 MW
Turbine capacity1.9 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20352010201520202025today1234567
  1. 1Jan 2009 — Application submitted
  2. 2Aug 2009 — Refused
  3. 3May 2010 — Permission granted
  4. 4May 2010 — Granted on appeal
  5. 5May 2011 — Permission expired
  6. 6Mar 2012 — Under construction
  7. 7Apr 2013 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3835.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 13 months. The register records a refusal in August 2009 before the scheme progressed. Permission was ultimately granted on appeal in May 2010. A planning permission on this site expired in May 2011. The scheme has been operating for about 13 years. That works out at 1.9 MW per turbine on average.

Nearby

See all wind farms in Humberside.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.