Rosehall Hill Forest Windfarm

19 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines19
Installed capacity24.7 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)E.ON UK
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted November 2005 Permission granted September 2006 Under construction August 2011 Operational February 2013

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4051.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 18 months. The scheme has been operating for about 13 years. That works out at 1.3 MW per turbine on average.

Nearby

See all wind farms in Highland.