Rosehill Wind Turbines

3 turbines · operational · Stirling

Wind farm facts

StatusOperational
County / regionStirling
Turbines3
Installed capacity2.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Green Cat Renewables
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 Project timeline Application submitted October 2012 Refused September 2013 Permission granted April 2014 Granted on appeal April 2014 Under construction May 2015 Operational December 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3651.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 7 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in April 2014. The scheme has been operating for about 11 years. That works out at 0.8 MW per turbine on average.