3 turbines · operational · Stirling
| Status | Operational |
|---|---|
| County / region | Stirling |
| Turbines | 3 |
| Installed capacity | 2.4 MW |
| Turbine capacity | 0.8 MW |
| Tip height | not recorded |
| Operator (or applicant) | Green Cat Renewables |
| Turbine manufacturer | Enercon |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3651.
The application was determined in about 18 months. Construction to first power took about 7 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in April 2014. The scheme has been operating for about 11 years. That works out at 0.8 MW per turbine on average.