Roskrow Wind Turbines

2 turbines · operational · Cornwall

Wind farm facts

StatusOperational
County / regionCornwall
Turbines2
Installed capacity1.7 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower (previously Cornwall Light and Power)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 Project timeline Application submitted December 2002 Refused February 2004 Permission granted February 2004 Granted on appeal February 2004 Operational December 2007

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3233.

What the register tells us

The application was determined in about 14 months. The register records a refusal in February 2004 before the scheme progressed. Permission was ultimately granted on appeal in February 2004. The scheme has been operating for about 19 years. That works out at 0.85 MW per turbine on average.