🌬️ Onshore wind farm

Rothes Wind (Cairn Uish)
Grampian

Recorded in WhichWindTurbine: 22 wind turbines in operation. Point the app at one of them to see its profile in real time.

22
turbines
50.6 MW
MW total
2.3 MW
per turbine

📍 22 turbines mapped — each dot is a turbine recorded in the database. Average position: 57.53643 N · 3.36701 W.

Rothes Wind (Cairn Uish)

22 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines22
Installed capacity50.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Natural Power Consultants
Turbine manufacturerBonus (now Siemens) (secondary source)
Turbine modelB2300 (secondary source)
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

○ Cross-checked reference — turbine make and model (secondary source)

Bonus (now Siemens) · B2300 · 22 turbines · 2.3 MW each

Source: Wikipedia, list of onshore wind farms in the United Kingdom (compiled from UKWED and The Wind Power), read on 2026-09-19. This is a compiled list, not a primary record. It is shown because two independent facts — turbine count and rated power — match the database exactly. Awaiting confirmation from a primary source.

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~202720052010201520202025today123
  1. 1Sep 2001 — Application submitted
  2. 2Jan 2003 — Permission granted
  3. 3Nov 2004 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3534.

What the register tells us

The application was determined in about 16 months. The scheme has been operating for about 22 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Grampian.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.