Saltend Wind Turbine

1 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines1
Installed capacity1.3 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)Yorkshire Water
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted December 2005 Permission granted March 2006 Operational November 2007 Permission expired March 2011

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2942.

What the register tells us

The application was determined in about 3 months. A planning permission on this site expired in March 2011. The scheme has been operating for about 19 years. That works out at 1.3 MW per turbine on average.