Screggagh

8 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines8
Installed capacity19.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Screggagh Windfarm
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted April 2005 Permission granted May 2008 Under construction July 2009 Operational March 2011 Permission expired May 2018

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3263.

What the register tells us

The application was determined in about 37 months. Construction to first power took about 20 months. A planning permission on this site expired in May 2018. The scheme has been operating for about 15 years. That works out at 2.44 MW per turbine on average.