Seamer Wind Farm - Hambleton

2 turbines · operational · Cleveland

Wind farm facts

StatusOperational
County / regionCleveland
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Infinis, previously Broadview Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 Project timeline Application submitted March 2009 Permission granted September 2009 Under construction October 2011 Operational November 2012

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3791.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 13 months. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.