Seamer Windfarm - Stockton on Tees

3 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Broadview Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted March 2009 Permission granted August 2009 Under construction April 2012 Operational November 2012 Permission expired August 2017

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3984.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 7 months. A planning permission on this site expired in August 2017. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in County Durham.