🌬️ Onshore wind farm

Seamer Windfarm - Stockton on Tees
County Durham

Recorded in WhichWindTurbine: 3 wind turbines in operation. Point the app at one of them to see its profile in real time.

3
turbines
6 MW
MW total
2 MW
per turbine

📍 3 turbines mapped — each dot is a turbine recorded in the database. Average position: 54.49343 N · 1.25738 W.

Seamer Windfarm - Stockton on Tees

3 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Broadview Energy
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20352010201520202025today1234
  1. 1Mar 2009 — Application submitted
  2. 2Aug 2009 — Permission granted
  3. 3Apr 2012 — Under construction
  4. 4Nov 2012 — Operational

The register also records a planning permission expiry in Aug 2017, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3984.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 7 months. A planning permission on this site expired in August 2017. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in County Durham.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.