Severn Trent Water - Stoke Bardolph Wind Turbine

1 turbines · operational · Nottinghamshire

Wind farm facts

StatusOperational
County / regionNottinghamshire
Turbines1
Installed capacity1.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Severn Trent Water
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 Project timeline Application submitted December 2012 Permission granted September 2013 Under construction March 2015 Operational December 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3897.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 9 months. The scheme has been operating for about 11 years. That works out at 1.5 MW per turbine on average.