🌬️ Onshore wind farm

Shepham Lane
East Sussex

Recorded in WhichWindTurbine: 5 wind turbines. Point the app at one of them to see its profile in real time.

5
turbines
12.5 MW
MW total
2.5 MW
per turbine

📍 3 turbines mapped — each dot is a turbine recorded in the database. Average position: 50.82613 N · 0.27415 E.

Shepham Lane

5 turbines · revised · East Sussex

Wind farm facts

StatusRevised
County / regionEast Sussex
Turbines5
Installed capacity12.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Galliford Try Renewables (GTR)
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2039201520202025today123456
  1. 1Feb 2013 — Application submitted
  2. 2May 2013 — Refused
  3. 3Jan 2015 — Permission granted
  4. 4Jan 2015 — Granted on appeal
  5. 5Aug 2016 — Under construction
  6. 6Jan 2017 — Operational

The register also records a planning permission expiry in Jan 2018, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

The register links a second scheme on this site (REPD ref 4326, Operational): 3 turbines · 2.5 MW each · applicant Foresight. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3725.

What the register tells us

That works out at 2.5 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.