Sisters

4 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines4
Installed capacity8.2 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)Infinis (formerly Novera Energy)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted September 2011 Permission granted February 2013 Under construction July 2015 Operational July 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4167.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 12 months. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.