12 turbines · operational · Co. Tyrone
| Status | Operational |
|---|---|
| County / region | Co. Tyrone |
| Turbines | 12 |
| Installed capacity | 27.6 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish and Southern Energy (SSE) |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4058.
The application was determined in about 53 months. Construction to first power took about 6 months. A planning permission on this site expired in March 2012. The scheme has been operating for about 15 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Co. Tyrone.