Slieveglass

3 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines3
Installed capacity6.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Slieveglass wind farm (Energia)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted January 2008 Refused April 2012 Permission granted June 2013 Granted on appeal June 2013 Under construction September 2017 Permission expired June 2018 Operational August 2018

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4065.

What the register tells us

The application was determined in about 65 months. Construction to first power took about 11 months. The register records a refusal in April 2012 before the scheme progressed. Permission was ultimately granted on appeal in June 2013. A planning permission on this site expired in June 2018. The scheme has been operating for about 8 years. That works out at 2.3 MW per turbine on average.