Solutia UK Ltd

2 turbines · operational · Gwent

Wind farm facts

StatusOperational
County / regionGwent
Turbines2
Installed capacity5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Solutia / Vestas
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted November 2008 Permission granted January 2009 Under construction September 2009 Operational December 2009 Permission expired January 2015

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3034.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 3 months. A planning permission on this site expired in January 2015. The scheme has been operating for about 17 years. That works out at 2.5 MW per turbine on average.