Southrigg

1 turbines · operational · Lanarkshire

Wind farm facts

StatusOperational
County / regionLanarkshire
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height125 m
Operator (or applicant)Southrigg WT
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted November 2014 Refused May 2015 Permission granted August 2015 Granted on appeal August 2015 Under construction August 2016 Operational October 2016 Permission expired August 2018

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4747.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 2 months. The register records a refusal in May 2015 before the scheme progressed. Permission was ultimately granted on appeal in August 2015. A planning permission on this site expired in August 2018. The scheme has been operating for about 10 years. That works out at 1.5 MW per turbine on average.