Spaldington Airfield

5 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines5
Installed capacity12.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Falck Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted November 2009 Refused September 2010 Permission granted September 2011 Granted on appeal September 2011 Permission expired September 2011 Under construction June 2013 Operational May 2016

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3700.

What the register tells us

The application was determined in about 22 months. Construction to first power took about 35 months. The register records a refusal in September 2010 before the scheme progressed. Permission was ultimately granted on appeal in September 2011. A planning permission on this site expired in September 2011. The scheme has been operating for about 10 years. That works out at 2.5 MW per turbine on average.