Spicer Hill Wind Farm

3 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines3
Installed capacity6.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)J G Pears Limited
Turbine manufacturerBonus
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 Original scheme Application submitted April 2009 Permission granted April 2010 Operational February 2013 Later scheme Application submitted November 2014 Refused February 2015

From application to operation, this scheme took about 4 years.

The register links a second scheme on this site (REPD ref 4791, Appeal Refused): 3 turbines · 2.3 MW each · 93 m tip height · applicant JG Pears Power. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2680.

What the register tells us

The application was determined in about 12 months. The scheme has been operating for about 13 years. That works out at 2.3 MW per turbine on average.