Srondoire Community Wind Farm

3 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Srondoire Wind Farmers LLP
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 Project timeline Application submitted July 2013 Permission granted December 2013 Under construction June 2014 Operational December 2015

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4328.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 18 months. The scheme has been operating for about 11 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Strathclyde.