St. Breock Re-Power

11 turbines · revised · Cornwall

Wind farm facts

StatusRevised
County / regionCornwall
Turbines11
Installed capacity10.4 MW
Turbine capacity0.94 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Generation Limited - previously E.on
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2001 2003 2005 2007 2009 2011 2013 2015 Original scheme Permission expired January 2000 Application submitted June 2002 Permission granted January 2003 Later scheme Application submitted March 2012 Permission granted October 2012 Under construction June 2014 Operational February 2015

The register links a second scheme on this site (REPD ref 4604, Operational): 5 turbines · 2.5 MW each · applicant REG & Blackrock. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4007.

What the register tells us

The application was determined in about 7 months. A planning permission on this site expired in January 2000. That works out at 0.95 MW per turbine on average.

Nearby

See all wind farms in Cornwall.