St Fergus Moss Wind Farm

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Greenspan Electric St Fergus Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 Project timeline Application submitted June 2010 Permission granted February 2012 Under construction March 2012 Operational December 2012

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2741.

What the register tells us

The application was determined in about 20 months. Construction to first power took about 9 months. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.