St Fergus Renewable Energy Park

2 turbines · under construction · Grampian

Wind farm facts

StatusUnder Construction
County / regionGrampian
Turbines2
Installed capacity3 MW
Turbine capacitynot recorded
Tip height119 m
Operator (or applicant)Ednie Farms
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2018 2019 2020 2021 2022 2023 2024 2025 Project timeline Application submitted December 2019 Refused December 2020 Permission granted July 2021 Granted on appeal July 2021 Under construction February 2023 Permission expired July 2024

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 7595.

What the register tells us

The application was determined in about 19 months. The register records a refusal in December 2020 before the scheme progressed. Permission was ultimately granted on appeal in July 2021. A planning permission on this site expired in July 2024. That works out at 1.5 MW per turbine on average.