St John Hill

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity7.7 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Auquhirie Land Company Ltd
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted July 2008 Permission granted December 2009 Operational March 2013

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2867.

What the register tells us

The application was determined in about 17 months. The scheme has been operating for about 13 years. That works out at 2.57 MW per turbine on average.