St Johns Wells Wind Cluster Extension

4 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines4
Installed capacity3.2 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Green Cat Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted January 2010 Permission granted June 2012 Under construction October 2013 Operational March 2015

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3840.

What the register tells us

The application was determined in about 29 months. Construction to first power took about 17 months. The scheme has been operating for about 11 years. That works out at 0.8 MW per turbine on average.