Stags Holt

9 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines9
Installed capacity18 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Powergen / Wind Prospects
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Scheme REPD 3129 Application submitted December 2001 Permission granted May 2002 Under construction April 2007 Operational October 2007 Scheme REPD 3741 Application submitted June 2007 Permission granted October 2008 Operational December 2010

From application to operation, this scheme took about 6 years.

The register links a second scheme on this site (REPD ref 3741, Operational): 1 turbines · 2 MW each · applicant E.ON UK. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3129.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 6 months. The scheme has been operating for about 19 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Cambridgeshire.