5 turbines · operational · Nottinghamshire
| Status | Operational |
|---|---|
| County / region | Nottinghamshire |
| Turbines | 5 |
| Installed capacity | 10.3 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | REG Power Management (John Laing/Peel Energy) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3739.
The application was determined in about 21 months. Construction to first power took about 9 months. The register records a refusal in March 2008 before the scheme progressed. Permission was ultimately granted on appeal in March 2009. A planning permission on this site expired in March 2000. The scheme has been operating for about 13 years. That works out at 2.06 MW per turbine on average.