2 turbines · operational · Grampian
| Status | Operational |
|---|---|
| County / region | Grampian |
| Turbines | 2 |
| Installed capacity | 4.6 MW |
| Turbine capacity | 1.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Green Cat Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
The register links a second scheme on this site (REPD ref 2708, Operational): 1 turbines · 1.3 MW each · applicant Green Cat Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2922.
The application was determined in about 18 months. The scheme has been operating for about 17 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Grampian.