Strathallan Wind Farm

9 turbines · under construction · Perth and Kinross

Wind farm facts

StatusUnder Construction
County / regionPerth and Kinross
Turbines9
Installed capacity20.7 MW
Turbine capacity2.3 MW
Tip height93 m
Operator (or applicant)Green Cat Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Project timeline Application submitted October 2015 Refused April 2017 Permission granted January 2019 Granted on appeal January 2019 Permission expired January 2022 Under construction February 2023

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2860.

What the register tells us

The application was determined in about 39 months. The register records a refusal in April 2017 before the scheme progressed. Permission was ultimately granted on appeal in January 2019. A planning permission on this site expired in January 2022. That works out at 2.3 MW per turbine on average.