Sunnyside wind cluster

2 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines2
Installed capacity1 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)Sunnyside Wind Farm
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 Project timeline Application submitted April 2013 Permission granted December 2013 Under construction June 2015 Operational November 2015

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4514.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 5 months. The scheme has been operating for about 11 years. That works out at 0.5 MW per turbine on average.