11 turbines · operational · Leicestershire
| Status | Operational |
|---|---|
| County / region | Leicestershire |
| Turbines | 11 |
| Installed capacity | 22 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Nuon UK |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3685.
The application was determined in about 20 months. Construction to first power took about 11 months. The register records a refusal in September 2009 before the scheme progressed. Permission was ultimately granted on appeal in December 2009. A planning permission on this site expired in December 2019. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.