Tangy Wind Farm Extension/Tangy 2

7 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines7
Installed capacity6 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)Scottish and Southern Energy (SSE)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Permission expired September 2000 Application submitted July 2004 Permission granted September 2005 Under construction May 2006 Operational June 2011

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4024.

What the register tells us

The application was determined in about 14 months. Construction to first power took about 61 months. A planning permission on this site expired in September 2000. The scheme has been operating for about 15 years. That works out at 0.86 MW per turbine on average.