Tedder Hill Wind cluster

3 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines3
Installed capacity7.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Ventient (formerly Infinis)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted May 2006 Refused September 2008 Permission granted January 2010 Granted on appeal January 2010 Under construction October 2012 Operational August 2013 Permission expired January 2017

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3749.

What the register tells us

The application was determined in about 44 months. Construction to first power took about 10 months. The register records a refusal in September 2008 before the scheme progressed. Permission was ultimately granted on appeal in January 2010. A planning permission on this site expired in January 2017. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.