The Grange Wind Farm

7 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines7
Installed capacity14 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted June 2009 Refused April 2010 Permission granted October 2010 Granted on appeal October 2010 Under construction September 2012 Operational March 2013

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3671.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 6 months. The register records a refusal in April 2010 before the scheme progressed. Permission was ultimately granted on appeal in October 2010. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.