7 turbines · operational · Lincolnshire
| Status | Operational |
|---|---|
| County / region | Lincolnshire |
| Turbines | 7 |
| Installed capacity | 14 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Renewable Energy Systems (RES) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3671.
The application was determined in about 16 months. Construction to first power took about 6 months. The register records a refusal in April 2010 before the scheme progressed. Permission was ultimately granted on appeal in October 2010. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.