The Hollies

2 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines2
Installed capacity2.6 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)National Wind Power
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 Project timeline Application submitted July 2002 Permission granted October 2004 Under construction September 2007 Operational January 2008

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3186.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 4 months. The scheme has been operating for about 18 years. That works out at 1.3 MW per turbine on average.