Recorded in WhichWindTurbine: 2 wind turbines in operation. Point the app at one of them to see its profile in real time.
📍 2 turbines mapped — each dot is a turbine recorded in the database. Average position: 52.99527 N · 2.26037 W.
2 turbines · operational · Staffordshire
| Status | Operational |
|---|---|
| County / region | Staffordshire |
| Turbines | 2 |
| Installed capacity | 1.9 MW |
| Turbine capacity | not recorded |
| Tip height | 77 m |
| Operator (or applicant) | Keele University |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register also records a planning permission expiry in May 2010, in the same month as, or before, the permission was granted: it refers to an earlier permission, left off the axis.
DevelopmentConstructionOperationAhead (repowering horizon at 22 years)
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 7312.
The application was determined in about 5 months. Construction to first power took about 9 months. A planning permission on this site expired in May 2010. The scheme has been operating for about 5 years. That works out at 0.95 MW per turbine on average.
| Data | Source | Extract |
|---|---|---|
| Site, capacity, status, planning milestones | Renewable Energy Planning Database (DESNZ, Open Government Licence v3) | Q2 2026, published 03/08/2026 |
| Turbine positions | OpenStreetMap contributors (ODbL) | 19/08/2026 |
| Manufacturer and model | OpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong. | 19/08/2026 |
Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.