Tilbury Docks

4 turbines · operational · Essex

Wind farm facts

StatusOperational
County / regionEssex
Turbines4
Installed capacity12 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Scottish Equity Partners
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted December 2007 Permission granted May 2008 Under construction September 2012 Operational March 2013

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3982.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 6 months. The scheme has been operating for about 13 years. That works out at 3 MW per turbine on average.