4 turbines · operational · Essex
| Status | Operational |
|---|---|
| County / region | Essex |
| Turbines | 4 |
| Installed capacity | 12 MW |
| Turbine capacity | 3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish Equity Partners |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3982.
The application was determined in about 5 months. Construction to first power took about 6 months. The scheme has been operating for about 13 years. That works out at 3 MW per turbine on average.