Tod Hill Farm Wind Turbines

4 turbines · operational · Falkirk

Wind farm facts

StatusOperational
County / regionFalkirk
Turbines4
Installed capacity12 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Falkirk Tod Hill Wind Limited
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted June 2011 Refused December 2011 Permission granted June 2012 Granted on appeal June 2012 Under construction April 2014 Operational January 2015 Permission expired June 2015

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3415.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 9 months. The register records a refusal in December 2011 before the scheme progressed. Permission was ultimately granted on appeal in June 2012. A planning permission on this site expired in June 2015. The scheme has been operating for about 11 years. That works out at 3 MW per turbine on average.