Toddleburn

12 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines12
Installed capacity27.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Scottish and Southern Energy (SSE)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted September 2004 Permission granted August 2005 Under construction April 2010 Permission expired August 2010 Operational October 2010

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3457.

What the register tells us

The application was determined in about 11 months. Construction to first power took about 6 months. A planning permission on this site expired in August 2010. The scheme has been operating for about 16 years. That works out at 2.3 MW per turbine on average.